Skip to content

Milestones

List view

  • We plan a last release for 32 bit machines soon, and that will also be the last of the 0.7s. So this may delay the date so it can become the first of the 0.8s. Now it is just for version 0.8.2!

    Overdue by 11 month(s)
    Due by March 31, 2025
    82/108 issues closed
  • Next stuff

    Overdue by 2 year(s)
    Due by November 6, 2023
    26/34 issues closed
  • This used to be 0.7.17 and for August/Sept/Oct 2023! Then it was 0.7.19 for a long time! We need to investigate the issues here as well (Version initially ready for the end of Pro Ruwa and possibly for wider publicity/dissemination - if all goes well might become Version 0.8? How optimistic I was! - anyway that's now the next one!) Many have been implemented. I include thosew mainly for the last workshop (Kenya Met) in our 2026 WMO contract!

    Due by March 5, 2026
    126/156 issues closed
  • Version ready for CIMH and Mozambique initiatives

    Overdue by 2 year(s)
    Due by July 15, 2023
    23/28 issues closed
  • Ready for e-learning course

    Overdue by 2 year(s)
    Due by December 31, 2023
    1/1 issues closed
  • Issues now for the March 2023 update!

    Overdue by 2 year(s)
    Due by March 31, 2023
    19/24 issues closed
  • Items to include so we are able to declare R-Instat as ready for broader promotion. Hopefully!

    Overdue by 2 year(s)
    Due by May 5, 2023
    10/11 issues closed
  • Hope to start the new year with this new version!

    Overdue by 3 year(s)
    Due by January 31, 2023
    9/10 issues closed
  • Was the August update - now for September and now October and now November! I hope, finally it can be available by early December in time for the CIMH workshop.

    Overdue by 3 year(s)
    Due by December 2, 2022
    26/42 issues closed
  • The July update

    Overdue by 3 year(s)
    Due by July 20, 2022
    5/9 issues closed
  • Items left over from 0.7.5

    Overdue by 3 year(s)
    Due by June 17, 2022
    16/21 issues closed
  • Update as to be in time for the AIMS course. Well we missed that! The next workshop is for Kenya Met (KMD) in the week starting 9 May. There is then one for GMet in the following week.

    Overdue by 3 year(s)
    Due by April 29, 2022
    88/133 issues closed
  • Hope for the solid version with the tables well advanced and hopefully more help included, if not in 0.8.2.

    Overdue by 10 month(s)
    Due by April 30, 2025
    245/342 issues closed
  • Issues with no current deadline. The current milestone always take priority over these. But if there are no obvious issues from the current milestone to do, tasks in here are the next tasks to do.

    No due date
    24/34 issues closed
  • Issues where the milestone is not yet clear or decided on. This is different from the 0.x milestone which contains Issues that have been agreed to have no fixed deadline yet.

    No due date
    100/127 issues closed
  • This milestone corresponds to a first 'functional' package where each of the prepare, describe and model menus have what we would consider a minimal functionality for a statistics package. There are currently no target deadlines for these improvements. Current estimates budget this at around $150K with an 6-12 month implementation period.

    No due date
    18/23 issues closed
  • This is a placeholder milestone for tasks which will be done after v0.4.0 but before v1.0.0. Tasks in here will eventually be moved to a specific version milestone e.g. v0.7.2.

    No due date
    126/142 issues closed
  • A long term plan for a rewrite with a new front end system to make R-Instat platform independent among other things.

    No due date
    2/2 issues closed
  • Long term first 'complete' version. No date or timescale set for this release yet, as it would require substantial additional resources to achieve. Current estimations cost this at around $500K with a 2-3 year implementation period.

    No due date
    9/15 issues closed