Supervisor: Dr. Amir Aryani
Tutor: Dr. Lynette Johns-Boast
Team Members: Hao, Kun, Andy, Zhaolian
Type: Tutor Meeting
Date: 05-05-2017
Time: Fri 1:00 p.m.
Facilitator: Andy, Hao, Kun, Zhaolian, Lynette, Observers
Note Taker:
Zhaolian
| Tables | Group Members | Lynette | Todo List/Decisions/Notes |
|---|---|---|---|
| Warmup | Go around all members | ||
| Progress Updates |
Kun’s meeting with NCI:
|
Advise:
|
Send this Meeting Agenda back to Lynette and all observers. |
Hao/Zhaolian’s task:
|
Questions raised:
|
||
| Project Review |
Quick Survey:
|
||
| Feedback Clarification |
Clarifications:
|
Suggestions:
|
|
Type: Client Meeting
Date: 13-03-2017
Time: Mon 4:00 p.m.
Facilitator: Amir, Hao, Kun, Andy, Zhaolian
Note Taker:
Kun
- Review the codes
[Everyone] - Think about how to separate the codes to components
[Everyone] - Write a blogpost on visualisation research graph using Neo4j and Gephi
[Hao, Zhaolian] - Definition of the Wiki structure
[Hao] - Finish the installation in Amir’s Ubuntu virtual machine, this Wednesday
[Hao, Zhaolian] - Swap data provider between Andy and Zhaolian
[Andy, Zhaolian]] - Arrange a meeting with NCI staff this week later or next week
[Amir, Kun] - Contact Uni Sydney developers
[Amir, Andy] - Preliminary plan for the first report in this semester
[Everyone]
- Information about the GitHub repositories
- Summary of the project
- Overview of the working component
- Plan for this semester including discussion about domain graphs, export process to Gephi and LeapMotion extension
- Preliminary plan for final presentation
[Everyone]
- Introducing gestures
- The contribution of each person
- The work cooperated with four data provider
- One of us might subject to availability of fund by ANU to attend a conference in Brisbane
Type: Client Meeting
Date: 07-03-2017
Time: Tue 4:00 p.m.
Facilitator: Amir, Hao, Kun, Andy, Zhaolian
Note Taker:
Hao
- General plan is that over the rest of the project, everyone will be involved in two dev tracks in parallel
One for gesture development for LeapMotion
One for extracting meaningful subgraphs from raw connection data - Install environment and get Gephi Virtual Control plugin run on all 3 OSs: Windows, Mac OS, Linux.
Report to Amir after peer meeting on Thursday 2-3pm
[Everyone] - Discuss and test the potential instability of LeapMotion integration with Gephi
[Amir, Hao] - Each member will be in charge of manipulating a graph for one of our customers for better demonstration purpose
happen early next week
[Detail See Issue#6]
Type: Client Meeting
Date: 27-02-2017
Time: Mon 4:00 p.m.
Facilitator: Amir, Hao, Kun, Andy, Zhaolian
Note Taker:
Hao
- Switch from Smartsheet to Github for project management
[Everyone] - Integrate ZenHub for better management
[Everyone] - Use Milestones for stage goals and issues for tasks for individuals
[Everyone] - Technical doc will be in project readme in code section, Github wiki servers as meeting agenda
[Everyone] - Pitch for TechLauncher 2017 sem 1
[Amir, Hao] - Prepare and learn packaging process
Plan is to make and release a software that everyone can download and use
[Everyone]